Infrastructure Project and Clover Flop

Another two weeks has passed since I planted the clover around the property and there still hasn’t been any significant growth. This may change over the coming weeks due to the rainy season starting, if it does then I’ll make sure to show it here. In the meantime, I’ve started another major project.

I’m calling this one the infrastructure project, it is basically putting all the plumbing and electrical wiring underground around the property to support future plans. I’m trying to do this in one shot as much as possible so the planning stage is very critical. I’ve created a map of where I think everything needs to go:

Infrastructure map

The first step was to lay out the locations for things such as the new garden area and the potting shed, then mark the plumbing and electrical connections based on these. Second, I placed markers all around the property for the remaining connections. There was some changes from this original design so I will have to make an updated map. Next, I measured the distanced for each item so I know how much pipe, connectors, and wire to buy.  This is where I am at now.

Once the items are purchased I’ll call in for a utility locate, this is where the power and cable company come in and mark the locations of their wires. I don’t have to worry about existing pipes since I am on well and septic and I know where they are located. Once this is done I’ll rent a trencher for a weekend and get everything underground. The final step will be hooking it all up.

Here’s a video walk through of where I am at now:

I’ll spend a couple of weeks double checking everything and getting the house connections ready, Stay tuned!